CONNECTED PROJECT · SDP24-0029

Taft House Pool Remodel and Site Update

3570 CELESTIAL AVE, CASTLE ROCK 80104

PROJECTSAPPROVED1 source
Project:OverviewTimelineTrades
AT A GLANCE

Project intelligence

Proposed update to existing pool, pool deck and pool amenities as well as proposed changes to existing drainage and grading to prevent site flooding.

Class
SITE DEVELOPMENT PLAN
Reported valuation
—
Square feet
—
Parcel SPN
235133402015
Zoning
Not linked yet
Land use
Not linked yet
HOW TO READ THIS PAGE

One project, multiple public signals.

The timeline combines evidence that may originally live in separate public systems. Source facts and our own inferred relationships remain visually distinct.

Public-source signal Our interpretation when labeled

Critical decisions should always be verified against the authoritative source linked on the record.

PROJECT TIMELINE

What happened, in order.

Follow the project from earlier public evidence through later construction activity.

2024-11-13
development projectSource fact

Taft House Pool Remodel and Site Update

Proposed update to existing pool, pool deck and pool amenities as well as proposed changes to existing drainage and grading to prevent site flooding.

APPROVEDCastle Rock Development Activity Map
Open authoritative source →
TRADE INTELLIGENCE

Likely work scopes on this project

Built from connected permits, project descriptions and other public signals. A match indicates likely involvement, not an open bid.

Browse all trades →
Source-backed98%

Carpentry / Framing

The public record directly references carpentry / framing work. Project signal (development project): The public record directly references carpentry / framing work.

See Carpentry / Framing activity →
Source-backed98%

Excavation / Grading

The public record directly references excavation / grading work. Site-development work commonly requires grading and earthwork. Project signal (development project): The public record directly references excavation / grading work.

See Excavation / Grading activity →
Likely85%

Site Utilities

Site-development work commonly requires underground utilities.

See Site Utilities activity →
Likely82%

General Contractor

Remodel/alteration work commonly requires coordinated construction management. Project signal (development project): Remodel/alteration work commonly requires coordinated construction management.

See General Contractor activity →
Likely78%

Concrete

Site-development work commonly includes concrete flatwork/curbs.

See Concrete activity →
Likely76%

Landscaping

Site plans commonly include landscape installation/restoration.

See Landscaping activity →
Likely76%

Paving / Asphalt

Site-development work commonly includes drives, roads, or parking areas.

See Paving / Asphalt activity →
Likely70%

Electrical

Remodels often require electrical modifications. Project signal (development project): Remodels often require electrical modifications.

See Electrical activity →
Likely66%

Drywall

Remodels commonly include partitions/drywall. Project signal (development project): Remodels commonly include partitions/drywall.

See Drywall activity →
Likely66%

HVAC / Mechanical

Remodels often require HVAC/mechanical modifications. Project signal (development project): Remodels often require HVAC/mechanical modifications.

See HVAC / Mechanical activity →
Likely64%

Plumbing

Remodels can require plumbing modifications. Project signal (development project): Remodels can require plumbing modifications.

See Plumbing activity →
Likely62%

Irrigation

Landscape/site-development work may require irrigation systems.

See Irrigation activity →